Completion of Work Activities under the Response Action Plan and Commencement of Construction

Work under the Response Action Plan was completed in June 2018. The final steps included completion of the Soil Vapor Extraction (SVE), completion of a second ground water injection to further reduce TCE levels in selected areas in the southwest portion of the property, and decommissioning of the 35 SVE wells and selected monitoring wells. Warmington’s consultant has provided a Final Report of the remediation activities to the EPA, which is currently under review.

The completion of the work activities under the Response Action Plan cleared the way for construction to begin at the site. Site work commenced again on August 20, 2018 with the completion of the grading activities. Installation of underground utilities will begin September 5, 2018. Home building will begin in late October 2018 and last through the summer of 2019.