TASK START FINISH DURATION
Soil Vapor Extraction 09/25/17 07/23/18 285d
SVE Well Installation 09/28/17 10/05/17 6d
Soil Gas Monitoring Well Installation 09/25/17 09/28/17 4d
Baseline Soil Gas Sampling 09/28/17 10/02/17 3d
Initial Vapor Extraction (North) 10/09/17 01/10/18 90d
Initial Vapor Extraction (South) 10/09/17 01/10/18 90d
Initial Rebound Evaluation (North) 01/15/18 04/15/18 91d
Initial Rebound Evaluation (South) 01/15/18 04/15/18 91d
Secondary Vapor Extraction (North, if necessary) 04/23/18 07/23/18 6d
Secondary Vapor Extraction (South, if necessary) 04/23/18 07/23/18 6d
Groundwater Bioaugmentation 09/08/17 04/25/18 227d
Groundwater Injections 09/08/17 09/29/17 10d
Monitoring Well Installations and Development 09/08/17 09/12/17 3d
Baseline Groundwater Sampling 09/15/17 09/15/17 1d
First Groundwater Sampling 12/15/17 12/18/17 2d
Second Groundwater Sampling 03/15/18 03/16/18 2d
Second GW Injection (if necessary) 04/16/18 04/25/18 8d
Final Response Action Completion Report 06/04/18 06/18/18 11d
EPA Approval and Notice of Response Action Completion 06/21/18 07/13/18 19d