ID TASK NAME DURATION START FINISH PREDECESSORS
2 Tentative Map Approval 0 days Tue 6/9/15 Tue 6/9/15
3 Plan Approval 248 days Thu 2/18/16 Mon 1/30/17
17 Final Map 465 days Wed 7/20/16 Tue 5/1/18
23 EPA provide conditional approval to City 1 day Wed 5/23/18 Wed 5/23/18
24 City issue Site Permit 1 day Fri 7/27/18 Fri 7/27/18 23FS+46 days
25 City issue tree removal permit 1 day Fri 7/27/18 Fri 7/27/18 23FS+46 days
26 Demolition 103 days? Mon 5/2/16 Wed 9/21/16
41 EPA Removal Action 9‐26‐16 112 days? Wed 9/7/16 Thu 2/9/17
42 Engeo to provide cost estimate for pilot well,
GW injections and SVE
6 days Mon 12/5/16 Mon 12/12/16
43 Engeo to drill Pilot well to determine area of influence 3 days Mon 12/19/16 Wed 12/21/16
44 EPA Community Outreach Meeting 1 day Thu 1/19/17 Thu 1/19/17
45 Soil Vapor Extraction 203 days Mon 9/11/17 Wed 6/20/18
49 EPA provide full site approval to City 1 day? Thu 6/21/18 Thu 6/21/18 48
50 Site Work 173 days? Wed 4/18/18 Fri 12/14/18
74 Issue Model Building permit 1 day? Thu 10/25/18 Thu 10/25/18 24
75 Model Start 1 day Mon 10/29/18 Mon 10/29/18 72SS+10 days
76 Production Homes Building 170 days Mon 1/7/19 Fri 8/30/19